What is First Fix and Second Fix in Electrical Work?
By Azzeddine Kebbi, NAPIT-registered electrician and director of Kebbi Electrical Services · Updated undefined
undefined
What is first fix?
First fix is the stage of electrical work carried out before the walls and ceilings are plastered or boarded. At this point, cables are run through the structure of the building — behind stud walls, through joists, and chased into masonry. Back boxes for sockets and switches are fixed to the wall, and the consumer unit is positioned and wired up internally. No sockets, switches, or light fittings are fitted yet — just the cables and back boxes are in place, ready for the builder to plaster over. First fix must be completed before plastering begins.
What is second fix?
Second fix happens after plastering and decoration are complete. The electrician returns to connect up the cables and fit the finished plates — sockets, switches, and light fittings. The consumer unit is also fully wired and commissioned at this stage. Second fix is cleaner work than first fix, but it must wait until the walls are dry and all decoration is finished, otherwise the new fittings could be damaged.
Why the order matters
Getting the sequence right saves time and money. If you plaster before first fix is finished, you risk having to cut open finished walls to run cables. If you install sockets before painting, they will get paint on them. The correct build sequence is: first fix electrics → plastering → second fix electrics → decoration. Talk to your electrician and your builder at the start of the project to agree the programme — a few minutes of planning can prevent expensive re-work.
Common questions
When does first fix electrical work happen?
First fix happens before the walls are plastered or boarded. All cables are run through the structure, back boxes are fixed, and the consumer unit carcass is in place. The plasterer cannot start until first fix is signed off.
When does second fix electrical work happen?
Second fix happens after plastering and decoration are complete. The electrician returns to connect the cables, fit sockets, switches and light fittings, and commission the consumer unit. The property should be fully dry and painted before second fix begins.
What is included in a first fix quote?
A first fix quote typically covers: running all cables through the structure, fixing back boxes for sockets and switches, installing the consumer unit carcass, running cables for lighting points, and any specialist circuits (kitchen, bathroom, outdoor, EV charger). It does not include the finished socket and switch plates — those come with second fix.
What is included in a second fix quote?
Second fix includes: fitting socket and switch faceplates, connecting lighting and fitting light fittings, connecting the consumer unit and testing all circuits, issuing an Electrical Installation Certificate, and testing to confirm the installation meets BS 7671 wiring regulations.
Can first fix and second fix be done by different electricians?
Yes, though it is simpler to use the same contractor for both stages. If you change electricians between stages, the second fix electrician will need to inspect and test the first fix work before connecting it. This can add time and cost — make sure the new electrician is comfortable taking on someone else's first fix.
How long after first fix can second fix happen?
There is no set minimum, but the walls need to be fully dry before second fix begins. For a new plaster finish this usually means waiting at least four to six weeks, though this varies depending on the thickness of the plaster, the temperature, and the ventilation. Fitting sockets into damp walls can cause damp to migrate behind the back box.